M25 closure – live: Heavy traffic J9 and 10 as drivers ‘ignore’ diversion route

M25 closure – live: Heavy traffic J9 and 10 as drivers ‘ignore’ diversion route
Closed M25 drone footage captures workers demolishing bridge

Good progress has been made on the first full day of the M25’s weekend closure as workers lifted the beams that will form the new bridge into place.

The motorway – which is Britain’s busiest – closed in both directions between junctions 9 and 10 in Surrey from 9pm on Friday while concrete beams for a new bridge are installed.

It will reopen at 6am on Monday.

Diversion routes take cars on a 19-mile journey on A roads, crossing from Surrey into London’s Ulez area, though National Highways has assured drivers “no enforcement action will be taken”.

However, the highways authority said anyone who ignores official diversion signs in an attempt to find shorter alternative routes will be liable for the £12.50 daily Ulez fee if their vehicle does not meet minimum emissions standards.

Simon Elliott, National Highways senior project manager, said it was “important that drivers follow the diversion route in place” to keep traffic moving well.

1715417291

Pinned post: M25 closed in both directions between Junctions 9 and 10 – mapped

Map below shows section of M25 motorway that is closed until Monday morning.

Matt Mathers11 May 2024 09:48

1715491815

Watch: Drone footage captures scale of M25 closure as new bridge beams installed

Drone footage has captured the sheer scale of this weekend’s M25 closure as new bridge beams are installed.

The motorway – which is Britain’s busiest – will be closed in both directions between junctions 9 and 10 in Surrey from 9pm on Friday (10 May) until 6am on Monday (13 May) while concrete beams for a new bridge are installed.

Diversion routes will take cars on a 19-mile journey on A roads, crossing from Surrey into London’s Ulez area, though National Highways has assured drivers “no enforcement action will be taken”.

Barney Davis12 May 2024 06:30

1715488200

ICYMI: Drivers warned over Ulez charges if they ignore diversions

National Highways said anyone ignoring diversion signs in an attempt to find shorter alternative routes will be liable for the £12.50 daily Ulez fee if their vehicle does not meet minimum emissions standards.

Full report:

Barney Davis12 May 2024 05:30

1715484495

Drone footage of M25 closures as beams for new bridge installed

Barney Davis12 May 2024 04:28

1715477415

ICYMI: Why is the closure happening?

National Highways says it is necessary for “the installation of a bridge and gantry” as part of a £317 million project to improve junction 10 – which handles 300,000 motorists per day.

“Our improvements will reduce congestion, create a smoother flow of traffic and provide safer journeys for thousands every day,” National Highways says.

The organisation is promising:

  • A larger roundabout with extra lanes to increase capacity.
  • Free flow left turns at all four corners of the junction.
  • New and safer routes for cyclists, pedestrians and horse riders.
  • Improvements to the local environment and wildlife.
Truck stop: the key interchange on the M25 closure diversion, at Tolworth in southwest London
Truck stop: the key interchange on the M25 closure diversion, at Tolworth in southwest London (Simon Calder)
Barney Davis12 May 2024 02:30

1715473800

Downturn in business claimed after M25 diversions

The 19-mile diversion route saw an “unusually low volume of traffic”, with residents and local businesses reporting quiet roads and reduced footfall in their towns and villages.

Councillor Rod Ashford from the Reigate and Banstead Borough Council told the PA news agency that, at around 5pm, traffic around junction 8, where the diversion route starts, was “free-flowing with an unusually low volume of traffic”.

He added: “Given the A217 would be a route to divert M25 traffic to Epsom and around (to the) M25 junction 9, traffic in my area is quiet.”

Meanwhile, in Epsom, a town on the diversion route, workers at Blacks Burgers told the PA news agency there had been a “downturn in business and walk-in trade” compared to last weekend and corresponding with the road closure, whilst the area in general seemed quieter.

National Highways previously urged drivers to only travel the route if necessary, to avoid the closure and to complete their journeys in other ways if possible.

The M25 closure is the second of five planned weekend closures which come as part of a £317 million project to improve junction 10.

Barney Davis12 May 2024 01:30

1715470095

In Pictures: M25 repairs see Bridge winched into place

(Jordan Pettitt/PA Wire)
(Jordan Pettitt/PA Wire)
(Jordan Pettitt/PA Wire)
Barney Davis12 May 2024 00:28

1715466122

More motorists ignoring diversions

National Highways said they had seen an increasing number of motorists choosing to ignore the diversion route, starting at junction 8, and instead continuing on the motorway to the next junction.

Simon Elliott, National Highways senior project manager, said it was “important that drivers follow the diversion route in place”.

He said in a statement: “It is the most effective way for people travelling clockwise along the M25 to reach their destination and will help keep traffic moving as well as possible during this weekend’s closure.

“Coming off at junction 9 means non-freight drivers will end up travelling behind or alongside HGVs which is something we are actively trying to avoid and is likely to have a negative impact on travel times, congestion and the communities they pass through.”

Barney Davis11 May 2024 23:22

1715463002

Will M25 diversion drivers be charged ULEZ?

Diversion routes take cars on a 19-mile journey on A roads, crossing from Surrey into London’s Ulez area, though National Highways has assured drivers “no enforcement action will be taken”.

However, the highways authority said anyone who ignores official diversion signs in an attempt to find shorter alternative routes will be liable for the £12.50 daily Ulez fee if their vehicle does not meet minimum emissions standards.

Failure to pay the charge when required can result in a £180 fine, reduced to £90 if paid within 14 days.

Barney Davis11 May 2024 22:30

1715458922

Mapped: 19-mile diversion route will be in place which uses the A3 and the A240

Barney Davis11 May 2024 21:22